Chapter 7: WxCC Migration Execution (Phase 2) -- 7.1 Pre-Migration Readiness

7.1 Pre-Migration Readiness

7.1.1 Phase 1 Dependency

+-----------------------------------------------------------------------------+
|              WXCC MIGRATION - PHASE 1 DEPENDENCY                            |
+-----------------------------------------------------------------------------+
|                                                                             |
|  [!]️ CRITICAL: UCCX REQUIRES CUCM FOR CTI CONNECTIVITY                      |
|                                                                             |
|  DEPENDENCY CHAIN:                                                         |
|  -----------------                                                         |
|                                                                             |
|  +-------------+     CTI (JTAPI)    +-------------+                        |
|  |    UCCX     |<-------------------|    CUCM     |                        |
|  |  (Contact   |                    |  (Call      |                        |
|  |   Center)   |                    |  Control)   |                        |
|  +-------------+                    +-------------+                        |
|        |                                   |                               |
|        |                                   |                               |
|        |    MIGRATION IMPACT:              |                               |
|        |    -----------------              |                               |
|        |                                   |                               |
|        v                                   v                               |
|  Once CC agents move to             Once CUCM is decommissioned,          |
|  Webex Calling (Phase 1             UCCX loses CTI connectivity.          |
|  Batch 5), they cannot              No parallel operation possible.       |
|  receive UCCX routed calls.                                               |
|                                                                             |
|  IMPLICATION:                                                              |
|  ------------                                                              |
|  WxCC cutover is effectively a BIG BANG for contact center.               |
|  Phase 1 completion is a HARD GATE for Phase 2.                           |
|  Rollback = Full stack rollback (Webex Calling -> CUCM -> UCCX)             |
|                                                                             |
+-----------------------------------------------------------------------------+

7.1.2 Prerequisites Checklist

+-----------------------------------------------------------------------------+
|              WXCC MIGRATION - PREREQUISITES CHECKLIST                       |
+-----------------------------------------------------------------------------+
|                                                                             |
|  PHASE 1 COMPLETION (MANDATORY)                                            |
|  -----------------------------------------------------------------------   |
|  [ ] All 175 CC agents migrated to Webex Calling (Chapter 7 P1 Batch 5)   |
|  [ ] CC agent desk phones registered to Webex Calling                     |
|  [ ] Webex App deployed to all CC agents                                  |
|  [ ] PSTN connectivity validated (LGW India, CCPP EMEA/US)               |
|  [ ] Phase 1 48-hour stability confirmed for CC agents                    |
|  [ ] CUCM decommission NOT started (rollback path preserved)              |
|                                                                             |
|  CHAPTER 6 IMPLEMENTATION (MANDATORY)                                      |
|  -----------------------------------------------------------------------   |
|  [ ] WxCC tenant activated (India DC)                                     |
|  [ ] All 175 agent licenses assigned                                      |
|  [ ] 6 Entry Points configured                                            |
|  [ ] 10 Queues configured                                                 |
|  [ ] 18 Skills created                                                    |
|  [ ] 12 Skill Profiles created                                            |
|  [ ] 8 Teams configured                                                   |
|  [ ] 9 Flows built and validated                                          |
|  [ ] 87 Audio prompts uploaded (62 EN + 25 HI)                           |
|  [ ] Virtual Agent "Abhi" integrated (Dialogflow CX)                     |
|  [ ] Salesforce connector configured                                      |
|  [ ] Recording enabled (100% all calls)                                   |
|  [ ] PCI auto-pause configured (Billing queue)                           |
|  [ ] All 20 test scenarios passed (Chapter 6.10.2)                       |
|                                                                             |
|  INFRASTRUCTURE                                                            |
|  -----------------------------------------------------------------------   |
|  [ ] DNS entries prepared for cutover                                     |
|  [ ] Toll-free number porting request submitted (if applicable)          |
|  [ ] SD-WAN QoS validated (ABV-SDWAN-2024)                               |
|  [ ] India DC data residency confirmed                                    |
|                                                                             |
|  TRAINING                                                                  |
|  -----------------------------------------------------------------------   |
|  [ ] Agent training curriculum finalized                                  |
|  [ ] Supervisor training curriculum finalized                             |
|  [ ] Training environment provisioned (sandbox tenant)                    |
|  [ ] Training schedule published                                          |
|                                                                             |
|  OPERATIONS                                                                |
|  -----------------------------------------------------------------------   |
|  [ ] Cutover runbook reviewed and signed off                             |
|  [ ] Rollback procedures documented                                       |
|  [ ] Hypercare support schedule confirmed                                 |
|  [ ] Help desk briefed on WxCC support                                   |
|  [ ] Vendor TAC cases opened (preventive)                                |
|                                                                             |
+-----------------------------------------------------------------------------+

7.1.3 Go/No-Go Gate

Gate Criteria Owner Status
G1 Phase 1 CC agents stable 48+ hours Voice Eng Lead [ ]
G2 Chapter 6 implementation 100% complete WxCC Eng Lead [ ]
G3 All 20 test scenarios passed QA Lead [ ]
G4 Agent training 100% complete (per wave) Training Lead [ ]
G5 Cutover runbook signed off Project Manager [ ]
G6 Rollback plan validated Voice Eng Lead [ ]
G7 Business owner approval CC Operations Mgr [ ]
G8 No P1/P2 open defects QA Lead [ ]

Decision: All gates MUST be passed before cutover proceeds.