Chapter 7: WxCC Migration Execution (Phase 2) -- 7.2 Migration Wave Planning

7.2 Migration Wave Planning

7.2.1 Overall Schedule

+-----------------------------------------------------------------------------+
|              WXCC MIGRATION - OVERALL TIMELINE                              |
+-----------------------------------------------------------------------------+
|                                                                             |
|  WEEK    | PHASE                | ACTIVITIES                               |
|  ========================================================================  |
|                                                                             |
|  Week 1-2  | PREPARATION        | Training curriculum development         |
|            |                    | Sandbox environment setup               |
|            |                    | Final Chapter 6 validation              |
|            |                    | Cutover runbook finalization            |
|                                                                             |
|  Week 3-4  | TRAINING           | Wave 1 agent training (Chennai)         |
|            | (Wave 1)           | Supervisor training                     |
|            |                    | UAT with business SMEs                  |
|                                                                             |
|  Week 5    | WAVE 1 CUTOVER     | Chennai (30 agents)                     |
|            | (Pilot)            | Weekend cutover                         |
|            |                    | 5-day stabilization                     |
|                                                                             |
|  Week 6    | TRAINING           | Wave 2 agent training (London, NJ)      |
|            | (Wave 2)           |                                         |
|                                                                             |
|  Week 7    | WAVE 2 CUTOVER     | London (15) + New Jersey (10)          |
|            |                    | Weekend cutover                         |
|            |                    | 5-day stabilization                     |
|                                                                             |
|  Week 8-9  | TRAINING           | Wave 3 agent training (Mumbai)          |
|            | (Wave 3)           | 120 agents - largest batch              |
|                                                                             |
|  Week 10   | WAVE 3 CUTOVER     | Mumbai HQ (120 agents)                  |
|            | (Final)            | Weekend cutover                         |
|            |                    | 24x7 operation - highest risk           |
|                                                                             |
|  Week 11-12| HYPERCARE          | Enhanced support                        |
|            |                    | Issue resolution                        |
|            |                    | Performance tuning                      |
|                                                                             |
|  Week 13   | STABILIZATION      | Handover to BAU operations             |
|            |                    | UCCX decommission planning              |
|            |                    | Project closure                         |
|                                                                             |
+-----------------------------------------------------------------------------+

7.2.2 Wave Migration Plan

Wave Site Agents Teams Weekend Risk Level
Wave 1 (Pilot) Chennai 30 Chennai_Support, India_Digital_Team Week 5 LOW
Wave 2 London + New Jersey 25 EMEA_Team, Americas_Team Week 7 MEDIUM
Wave 3 Mumbai HQ 120 India_Sales, India_Support, India_TechSupport, India_Billing Week 10 HIGH
TOTAL 4 Sites 175 8 Teams 3 Weekends

Wave Selection Rationale:

Wave Rationale
Wave 1 - Chennai Lowest risk: 30 agents, 9AM-9PM hours (not 24x7), single timezone, provides pilot learnings
Wave 2 - London/NJ Medium risk: 25 agents, business hours only, tests multi-region routing
Wave 3 - Mumbai Highest risk: 120 agents, 24x7 operation, primary support hub - benefits from Wave ½ learnings

7.2.3 Wave 1 Detailed Schedule (Chennai Pilot)

Day Date Activity Owner Hours
Pre-Week
Mon-Fri Week 3-4 Agent training (30 agents) Training Lead 2hr/day
Fri Week 4 Training completion sign-off Training Lead -
Fri Week 4 Go/No-Go decision call PM + Leads 30 min
Cutover Weekend
Fri 6:00 PM IST Cutover start - UCCX disable Voice Eng -
Fri 6:30 PM Entry Point DNS/routing switch Voice Eng -
Fri 7:00 PM Agent Desktop login validation CC Ops -
Fri 8:00 PM Test calls (all scenarios) QA 1 hr
Fri 9:00 PM Issue resolution window All 3 hr
Sat 9:00 AM Day 1 Live - first customer calls CC Ops -
Sat All day Enhanced monitoring Voice Eng + CC Ops 12 hr
Sun All day Stabilization Voice Eng 12 hr
Week 5 (Stabilization)
Mon-Fri Week 5 Production monitoring CC Ops -
Fri Week 5 Wave 1 sign-off CC Ops Manager -

7.2.4 Wave 2 Detailed Schedule (London + New Jersey)

Day Date Activity Owner Hours
Pre-Week
Mon-Fri Week 6 Agent training (25 agents) Training Lead 2hr/day
Fri Week 6 Go/No-Go decision call PM + Leads 30 min
Cutover Weekend
Sat 2:00 AM UTC Cutover start (off-hours all regions) Voice Eng -
Sat 2:30 AM Entry Point routing switch (EMEA/US) Voice Eng -
Sat 3:00 AM Agent Desktop login validation CC Ops -
Sat 4:00 AM Test calls (EMEA + Americas flows) QA 1 hr
Sat 9:00 AM UK Day 1 Live - London CC Ops -
Sat 9:00 AM ET Day 1 Live - New Jersey CC Ops -
Week 7 (Stabilization)
Mon-Fri Week 7 Production monitoring CC Ops -
Fri Week 7 Wave 2 sign-off CC Ops Manager -

7.2.5 Wave 3 Detailed Schedule (Mumbai HQ)

Day Date Activity Owner Hours
Pre-Week
Week 8-9 Agent training (120 agents - 4 batches) Training Lead 2hr/day
Fri Week 9 Training completion sign-off Training Lead -
Fri Week 9 Final Go/No-Go decision call PM + Leads 1 hr
Cutover Weekend
Sat 12:01 AM IST Cutover start (lowest call volume) Voice Eng -
Sat 12:30 AM India Entry Points routing switch Voice Eng -
Sat 1:00 AM Agent Desktop login (night shift) CC Ops -
Sat 2:00 AM Test calls (all India flows) QA 1 hr
Sat 3:00 AM Issue resolution window All 3 hr
Sat 6:00 AM Day shift handover CC Ops -
Sat-Sun All day Enhanced 24x7 monitoring Voice Eng + CC Ops 48 hr
Week 10 (Stabilization)
Mon-Fri Week 10 24x7 production monitoring CC Ops -
Fri Week 10 Wave 3 sign-off CC Ops Manager -